- Deploy REW of appropriate grade
- Arrange power suspension
- PITC Work for Distribution Circuit
- Visual inspection
- Continuity test for protective conductors
- Continuity test for ring final circuit conductors
- Insulation resistance test
- Polarity test
- Earth electrode resistance test
- Earth fault loop impedance test
- Functional test for protective devices
- PITC Work for Low Voltage Switchboard
- Isolation and proved dead
- Cleaning
- Visual inspection
- Contact resistance test
- Insulation resistance test
- Secondary injection test
- Functional test for protective devices
- Check indication devices
- Record all inspection and testing results
- Resume power
- Issue periodic test certificate and testing records
- Submit periodic test certificate and testing records for EMSD’s endorsement
Guideline for Periodic Inspection, Testing and Certification (PITC) Work